Since 1965

çoruh river altıparmak dam and hpp project

Project Location

Artvin, Turkey

Client

General Directorate Of Electrical Power Resources Survey And Development Administration (EİEİ)

Project Description

Feasibility study for Altıparmak Dam and HPP Çoruh River Basin, on Barhal creek. The dam is double-curvature thin arch type and 150 m high from foundation. Installed capacity of power plant is 50 MW.


Provided Services

  • Review of hydrological studies
  • Operation studies for different dam heights and installed capacities
  • Determination of optimum dimensions
  • Dam stability studies
  • Design of dam body, spillway, tunnels, power plant and other related structures
  • Quantity-cost estimates
  • Financial analysis of alternatives
  • Economic evaluation of the project.

Contact

Musa Çetinkaya

Musa Çetinkaya 

Civil Engineer M.Sc. 

cetinkaya@suis.com

Copyright © 2020 | Suiş Proje | All rights reserved. | Design By Cogen®Yazılım