çetin dam & hydropower plant feasibility report

Project Location

Siirt, Turkey

Client

Yüksel İnşaat A.Ş.

Project Description

Dam body is designed as rockfill embankment with clay core. Height of dam from thalweg is 150 m. Length of energy tunnel is 6000 m with 8 m diameter. Installed capacity of the HPP is 350 MW (3 units) and annual estimated production is 1230 GWh.

Provided Services

Hydrological studies covering water budget, reservoir operation studies and floods
Preliminary geotechnical and natural construction materials studies
Preliminary design of dam, diversion weirs, diversion and energy tunnels, conveyance canals and other related civil structures, power houses
Cost estimates for civil and electromechanical works
Financial analysis of the project