Project Description

Akcakale is located in Southeast Anatolia, on Syrian border. 85,000 people at 2027 year, 371 lt/sec project design discharge, 95 km sewer system and 4 km transmission line design, treatment plant is extended aeration type, 1,002 m³/hour project design discharge, 90% treatment, 20160 m³ (14 pieces) aeration pools, 8948 m³ final sedimentation tanks (2 pieces), 18816 m² sludge drying pools and 350 kW surface aerators.

 

Provided Services

Application designs
Quantity and cost estimates
Tender documents for sewage network, transmission line and treatment plant.